A. Anti-static floorInstallation requirements for the laying site

1. The laying of the floor should be carried out after the completion of indoor civil engineering and decoration construction;

2. The ground should be level, dry, free of debris and dust;

3. The available space under the floor, the laying of cables, circuits, waterways, air and other pipes and the air conditioning system should be completed before the installation of the floor;

4. The fixing of the base of large heavy equipment should be completed, and the equipment should be installed on the base. The height of the base should be the same as the height of the upper surface of the floor;

5. 220V / 50HZ power supply and water source are available on the construction site.

B. Floor installation and laying tools

Marble cutting saw, laser level tester, network laser scanner, blister level, tape measure, ink line, suction plate device, nut adjustment handle, cross screwdriver, vacuum cleaner, broom, mop;

防静电地板

C.Construction steps

1. Carefully check the flatness of the ground and the verticality of the wall. If any major defects are found or local reconstruction is required, it should be submitted to the relevant department of Party A

2. Pull the horizontal line and bounce the installation height of the floor onto the wall with ink lines to ensure that the floor after laying is at the same level, measure the length and width of the room and select the reference position, and pop up the grid grid of the support on the ground , To ensure that the laying is neat and beautiful, and at the same time minimize the cutting of the floor;

3. Adjust the support to be installed to the same required height and swing the support to the intersection of the ground grid line

4. Fix the truss beam to the support with mounting screws, and correct the truss beam one by one with a horizontal ruler and a square ruler so that they are both in the same plane and perpendicular to each other;

5. Use a suction plate to place a raised floor on the assembled truss beam;

6. If the remaining size near the wall is less than the length of the raised floor, you can use the method of cutting the floor to make up;

7. When laying the floor, use a bubble level to level it one by one. The height of the raised floor is adjusted by an adjustable support. During the laying process, it should be handled gently to prevent scratching the floor and damage the side strips. At the same time, it should be cleaned while laying. To avoid putting debris and dust under the floor;

8. When installing heavy equipment in the machine room, you can add a support under the floor of the equipment base to prevent the floor from being deformed;